Short answer: Computerised system validation (CSV) establishes, with proportionate evidence, that a configured system is suitable for its intended use. For Australian GMP manufacturing within scope, Annex 11 is included in the PIC/S Guide PE 009-17 adopted by the TGA. This guide turns Annex 11's audit-trail context into a practical assessment using a fictional SharePoint List; it does not establish that a particular tenant or organisation is regulated or compliant.
This focused CSV primer is general education, not a validation protocol or a determination of regulatory applicability. It introduces intended use, risk and evidence, then works through one audit-trail assessment rather than the full validation lifecycle. Scope and review frequency depend on intended use, applicable requirements and approved procedures.
Is Annex 11 a TGA requirement?
For Australian GMP manufacturing within scope, Annex 11 is included in the PIC/S Guide to GMP PE 009-17 adopted by the TGA. TGA guidance says PE 009-17 (25 August 2023) applies from 1 September 2025 to the manufacture of medicines, active pharmaceutical ingredients and sunscreens, unless an exemption under the Therapeutic Goods Regulations 1990 applies. Annexes 4, 5 and 14 are not adopted; Annex 11 is included. This is not a blanket requirement for every organisation or every SharePoint site. Confirm the regulated activity, product, exemptions and any applicable transition provisions with qualified Quality / Regulatory owners.
In PE 009-17 Annex 11, clause 9 addresses audit trails: consider system-generated records of GMP-relevant changes and deletions based on risk; document the reason for a change or deletion; and make audit trails available in a generally intelligible form for regular review. These are the source expectations this practical guide helps a reader assess, not a complete compliance checklist. See the TGA-hosted PE 009-17 Annexes, Annex 11 clause 9. For wider context, see Annex 11 in Plain English.
CSV basics before you review a log
Start with what the system is intended to do, not its product name. A basic CSV assessment can be organised around four questions:
- What is the intended use? Identify the process, users, important records and decisions that rely on the system, including what remains outside its scope.
- What could go wrong? Identify the requirements and credible failures that matter to that use, and explain which risks need controls or evidence.
- What evidence will show the controls work? Select proportionate checks, define expected results, and record what actually happened.
- Who assesses the result? Document gaps and have authorised owners decide the impact, disposition and any ongoing control or change assessment.
That is a learning frame, not a universal regulatory lifecycle. A full CSV approach may include planning, supplier and configuration evidence, requirements, risk assessment, verification, release decisions, and ongoing change control. The wider practical risk-based CSV guide covers that assurance lifecycle. This article narrows in on one question within it: what should you look for when assessing audit-trail evidence?
An audit trail is useful only when it supports a defined review question. A test that confirms “a log exists” does not establish that the right events are recorded, that the details are usable, or that the records are available for the required period.
What should an audit-trail review establish?
Write the evidence need before you open a history or search tool. Depending on the requirement, ask whether the available records let an authorised reviewer establish:
- Who acted: an identifiable account and, where relevant, the role or authority for the action.
- What happened: the record or setting affected and the action, such as creation, change, deletion, approval or a privileged configuration change.
- What changed: previous and new values where the requirement calls for them, not only a generic “item updated” event.
- When it happened: date, time and time zone where needed to understand sequence and timing.
- Why or with what authority: a reason or link to a controlled correction, investigation or approval record where the applicable procedure or requirement calls for it.
- Whether the evidence can be relied on: the relevant source, access, search scope, retention and protection from unauthorised alteration or deletion.
These are assessment questions, not a claim that every system must expose every detail in the same way. Establish the applicable requirement and test what the actual system and process provide.
SharePoint as an example, not a validation result
SharePoint List version history and Microsoft Purview audit records are different evidence sources. Microsoft's guidance says version history can show when an item changed, who changed it and changes to properties. It also explains that list managers can turn versioning on or off and that version settings can limit stored history. Check the actual list and its settings; do not infer them from product documentation.
The Microsoft 365 audit activity reference documents activities that may be available for SharePoint. Audit search also depends on the organisation's roles, subscription and retention arrangements. Check the current audit-search requirements and retention policy for the tenant. A documented activity name does not prove that a relevant event was captured, searchable, complete or retained in a particular environment.
For a SharePoint assessment, keep these sources distinct:
- List version history: inspect the history for the test item and the settings that govern version creation and retention.
- Purview audit records: verify the relevant documented activity, search permissions, time window and record details available to the reviewer.
- Process and source records: check any approved correction, investigation, change record or authoritative record that explains or authorises the event.
One source may answer part of the question while another supplies context. Do not treat a user-editable reason field as a protected audit trail or as proof of approval.
A practical assessment checklist
Use an approved test plan and synthetic records in a controlled environment. Do not perform destructive or privileged tests in a live register without explicit authorisation and a documented plan. Define the expected evidence before running the test.
| Requirement to assess | Controlled example | Evidence questions | Result |
|---|---|---|---|
| A new item can be traced to its creator and initial critical values. | Create one synthetic register item. | Can the reviewer identify the item, actor and time? Which source shows the initial values? | Not assessed in this article. |
| A critical field or status change leaves reviewable evidence. | Change a test item's status from “Open” to “Closed”. | Can the reviewer compare old and new values, identify the actor and time, and find the required reason or linked approval? | Not assessed in this article. |
| Deletion or recovery follows the approved process. | Test deletion and recovery only if included in the authorised plan. | Can the reviewer identify what was removed, by whom and when, and verify any required recovery or source record? | Not assessed in this article. |
| A privileged setting change is controlled. | Use an authorised test to change a versioning or access setting. | Can the action be traced to an authorised identity and matched to the approved change record? | Not assessed in this article. |
For each test, record the requirement, test identity, environment, item identifier, event time and time zone, exact search terms and filters, source inspected, export or evidence reference, expected result, observed result, and any limitation. Keep expected evidence separate from what was actually observed. No SharePoint tenant, list or audit event was inspected for this example.
Fictional example: a status change
The following invented example demonstrates how to compare expected evidence with a mock record. It is not a SharePoint or Purview test result, and it does not describe what either product always returns.
For fictional test item QREG-TEST-01, the procedure requires a status change to be attributable,
time-stamped, retain the previous and new values, and link to an approved correction record.
The controlled test changes “Open” to “Closed”.
| Assessment point | Fictional example |
|---|---|
| Expected evidence | The change history identifies the test account and time, shows “Open” to “Closed”, and points to correction COR-TEST-01. |
| Mock observation | A mock extract shows the test account, a time, and the old and new status. Its reason says “correction”, but it contains no link to COR-TEST-01. |
| Assessment | Gap: the mock extract shows who, when and what changed, but does not by itself establish the required supporting correction record. |
| Follow-up | Ask the record owner to locate and verify the approved correction. Ask the system owner whether the required link is available in another approved source. Have the authorised Quality owner assess and document the gap and disposition. |
These observations are fictional teaching details only. A real review must record the evidence actually returned by its authorised searches and must not assume version history or Purview always exposes these fields. A gap prompts investigation; it is not a conclusion that an improper action occurred.
What to look for when reviewing events
When reviewing actual events under an approved procedure, look for items that need explanation:
- a change after an approval, closure or other decision point;
- a missing previous value, unclear actor, unexpected account or timestamp sequence;
- a deletion, restoration or privileged setting change without the expected supporting record;
- repeated edits, unusual timing or a pattern that differs from the process being reviewed;
- a result that cannot be found because the search scope, permissions or retention are unclear.
These are prompts for follow-up, not proof of misconduct, system failure or non-compliance. Review the surrounding record and ask the responsible owner to explain an unexpected event. Do not impose a universal review frequency from this guide; use applicable requirements and approved procedures.
For each review, retain enough information for another authorised person to understand the work: system and record scope, period reviewed, events and sources examined, search parameters, observed details, linked records, conclusion, unresolved questions, owner and due date for follow-up. If a result is missing, verify the search range, filters, permissions, documented event coverage and retention before deciding what the absence means.
Choose the next step
For the broader assurance lifecycle, start with practical risk-based computerised system validation. For checks on collected GMP audit-trail entries, see what to look for when reviewing an audit trail. The worked SharePoint quality-register validation example covers the wider register assurance package. This article focuses on an Annex 11 clause 9 assessment using SharePoint as an example; the GMP review guide covers broader reviewer checks across collected entries.
For optional further learning, Online GMP Training describes its PIC/S Annex 11 – Computerised Systems course as covering risk-based computerised-system validation and audit-trail awareness. The course page also discusses draft EU/PIC/S material, so check the current TGA source above for Australian requirements. This provider course is not a regulatory authority.
Sources and scope
- Microsoft Support, How versioning works in lists and libraries, accessed 26 November 2026.
- Microsoft Learn, Audit log activities, page metadata dated 3 November 2026; accessed 26 November 2026.
- Microsoft Learn, Get started with auditing solutions, page metadata dated 18 February 2026; accessed 26 November 2026.
- Microsoft Learn, Manage audit log retention policies, page metadata dated 19 June 2026; accessed 26 November 2026.
- Therapeutic Goods Administration, Complying with the PIC/S Guide to Good Manufacturing Practice for medicinal products, accessed 26 November 2026. Confirm current local adoption, product scope and transition arrangements with qualified owners.
- Therapeutic Goods Administration, Good manufacturing practice requirements: PIC/S Guide PE 009-17, accessed 26 November 2026.
- Therapeutic Goods Administration, PIC/S Guide to GMP PE 009-17 Annexes, Annex 11, clause 9, edition dated 25 August 2023; accessed 26 November 2026.
- Online GMP Training, PIC/S Annex 11 – Computerised Systems course, accessed 26 November 2026. The provider page describes training on risk-based computerised-system validation and audit-trail awareness; it also references draft EU/PIC/S material.
This article is general education, not legal advice, an executed validation protocol, or evidence that a SharePoint configuration is suitable for a regulated use. Confirm product behavior, tenant configuration, source coverage, retention and regulatory applicability against authorised evidence for the actual system and process.